AH 2017 Street Maintenance Program will begin on Monday, July 31st.  The City has contracted with Clark Construction to complete this project.

Project work schedule for July 31st to August 11th

July 31 – Imlay - Mill and Pave; Arbutus - Mill and Pave; Columbine - Full Depth Repair and Pave
Aug 1: Ogden - Pave; Imlay, Arbutus, Columbine - Pave
Aug 2: Ogden - Pave; Abiso - Mill
Aug 3: Abiso - Pave
Aug 4: Pave above intersections
Aug 7: Elmview - Mill; Chichester - Mill
Aug 8: Elmview - Pave; Chichester - Pave
Aug 9: Tuxedo - Spot Repairs
 
*Streets will be closed to thru traffic, but open to residents. As work is being completed, do not park in the street. It is important to keep roadway dry during this process so please be mindful of sprinkler overspray into the roadway.

 
During repairs, the contractor will make every effort to direct and accommodate access to your property. All roads will be open after regular business hours and during the weekends.

Contact Jonathan Rodriguez, AH PW Superintendent, at 210-832-2252 or contact Public Works at 210-882-1518 for questions.

You must be a registered user to be able to comment.

Site Link Disclaimer

ah solo logo site  op solo logo site  th solo logo site

myAlamoHeights.com

provides several links to other web sites, resources or businesses. Such links do not constitute an expressed or implied endorsement or approval by myAlamoHeights.com of any website, or of the products or services of these websites may offer.


Alamo Heights
Olmos Park
Terrell Hills

Popular Last 14 Days

Popular Last 60 Days