Update Mar 11-Mar 17: Broadway/Hildebrand Project
Dear Citizens,
Work Schedule: March 11, 2013 through March 17, 2013
Monday 3-11-13 to Saturday 3-16-13:
Hildebrand between San Antonio River and Broadway St.:
• The two northern lanes (closest to University of Incarnate Word) will remain closed
• Continue construction of CPS electrical/telecommunication duct bank facilities to
include night time operations
Broadway at Burr Rd.:
• Burr Rd. at Broadway will remain closed
• Alamo Heights will be replacing their water line
Broadway from Allensworth to Hildebrand & from Burr Rd. to Katherine Ct.:
• AT&T will continue working on their underground facilities
Friday 3-15-13:
Broadway from Hildebrand to Perry Ct.:
• Close the southbound lane closest to The University of the Incarnate Word
• Begin construction of CPS electrical/telecommunication duct bank facilities
Sunday 3-17-13:
• No work scheduled
***Between 9AM to 4PM and 8PM to 5AM Monday-Friday Hildebrand will be reduced to one travel lane***
Work Schedule: March 11, 2013 through March 17, 2013
Monday 3-11-13 to Saturday 3-16-13:
Hildebrand between San Antonio River and Broadway St.:
• The two northern lanes (closest to University of Incarnate Word) will remain closed
• Continue construction of CPS electrical/telecommunication duct bank facilities to
include night time operations
Broadway at Burr Rd.:
• Burr Rd. at Broadway will remain closed
• Alamo Heights will be replacing their water line
Broadway from Allensworth to Hildebrand & from Burr Rd. to Katherine Ct.:
• AT&T will continue working on their underground facilities
Friday 3-15-13:
Broadway from Hildebrand to Perry Ct.:
• Close the southbound lane closest to The University of the Incarnate Word
• Begin construction of CPS electrical/telecommunication duct bank facilities
Sunday 3-17-13:
• No work scheduled
***Between 9AM to 4PM and 8PM to 5AM Monday-Friday Hildebrand will be reduced to one travel lane***